Project completion of SKK Ružomberok and WWTP Liptovská Teplá, Liptovské Sliače
Closing ceremony of project SKK Ružomberok and WWTP Liptovská Teplá, Liptovské Sliače was held on 7th of July 2016 in municipality office Liptovské Sliače. Beneficiary of this projects was Vodárenská spoločnosť Ružomberok. Works were financed by Cohesion Fund EU, National Budget, allowance of Vodárenská spoločnosť Ružomberok, and Operational Programme Environment.
Main goal of this projects was to divert and clean municipal sewage inside of Dolný Liptov region and to reach 99,2% connection of citizens to the public sewer. Project helped to connect about 5730 citizens, increased and reconstructed 40 116 meters of sewerage system, built 1698 connections in Liptovské Sliače, Liptovská Teplá, Ivachnová, Likavka and Ružomberok.
Atmosphere of this event you can see on the pictures below.